Click here to return Home.
Home
Calendar
The Association
The Neighborhood:
- Neighborhood Profile
- Maps
- History
- Businesses
- Parks & Rec
- Volunteer Gardens
- Schools
- Ward Updates
The Backyard
Links & Resources
NENA Review
Photo Gallery
Contact NENA

Phone: 612-724-5652,  Fax: 612-724-2770

 

The Neighborhood section Planting the Gateway Gardens
About NENA, its projects & programs, task forces, volunteers, mission, and staff. Living, shopping, and working in the four Nokomis East Neighborhoods. Issues and opinions, letters, humor, message boards, and related pieces. Useful links and contacts.

Lake Nokomis Community School - Keewaydin Campus Expansion


 
   
LNCS logo

Keewaydin Expansion Update #13 - March 15, 2013

The new campus expansion has transformed over the last few weeks. While most construction activities are happening on the interior, some exterior installations are also underway, such as brick masonry and roofing.

Starting on the first floor, most of the interior walls are framed with steel metal studs, and soon to follow will be gypsum board. These areas include the kitchen, bathrooms, classrooms and offices. Also on the first floor most of the concrete floor has been poured. The final areas to be poured are the cafeteria and main lobby areas. These areas are now being prepped and will be poured over the next few weeks.

The second floor concrete slab is complete and interior walls are being framed. With most of the metal studs constructed, gypsum is now being placed in some second floor areas. Duct work at the second floor is also being installed, and the mechanical room installation is underway. With most the mechanical units in place, CMU walls are being constructed to enclose the room. Work will continue on the installation of duct work and wall assemblies over the next few weeks.

At the exterior, brick masonry and sheathing is being installed. Brick is complete at the gym and is now being placed above new cafeteria and work will move to the first floor next week. Along with brick, the roofing has also been installed at north end of the new addition along the existing school.

Over the next few weeks work will be focused on the interior construction, and roofing and bricking the exterior.

Text,and photos in this update courtesy of RSP Architects, Minneapolis, MN.
(Received 3/20/13)

DID YOU KNOW?
Lake Nokomis Community School also maintains its own Construction Update page: http://lakenokomis.mpls.k12.mn.us/keewaydin_addition

 

Photo 12-1
Photo 13-1: Standing on the second floor balcony and new the space that will connect the new addition to the existing school. The space framed with metal studs will be one of many breakout rooms in the new addition. Click for larger image

Photo 12-2
Photo 13-2: Looking at the newly drywalled corridor at the second floor, the corridor will connect the second floor classrooms and is flanked by two stair wells at either end. Click for full image

Plan view 13
Viewpoint 13: Click image above to see full version of drawing showing where photos were taken and the direction of view. Click for full image

     

Keewaydin Expansion Update #12 - February 20, 2013

The Keewaydin campus has transformed over the last few weeks as the roofs were installed, exterior studs constructed and the expansion temporary enclosed.

Before temporarily enclosing the building, work was finished on the installation of the higher roofs above the classrooms, auditorium and common spaces. Work will soon begin on finishing the lower roofs, along with the roofs at the north links to the existing building.

While the higher roofs were installed, exterior steel studs were placed at first floor on the west and south walls. Exterior studs will be placed at the second floor after the concrete floor slab is poured.

The main focus recently has been to temporary enclose the building. Starting with east corridor, bathrooms and kitchen, work has began on heating the space and thawing the ground to prepare that area for the pouring of the concrete floor slab at both the first and second floor.

On the west side of building, work has begun on heating and enclosing the first and second floor. The second floor slab was poured at the south end and now preparing to pour the remaining second slab.

Expect work to continue on the interior concrete floor slabs, mechanical and electrical work as the gymís brick exterior finishes up over the next few weeks.

Text,and photos in this update courtesy of RSP Architects, Minneapolis, MN.
(Received 2/20/13)

 

Photo 12-1
Photo 12-1: Work continues on second floor concrete slab at the auditorium landing and mechanical room. Pictured is preparation of the second floor slab, over the steel decking, rebar is added and then the concrete will be poured.Click for larger image

Photo 12-2
Photo 12-2: Standing inside the recently enclosed west section of building and viewing the newly installed mechanical duct work and temporary enclosure. Other mechanical work has been started in the gym, first and second floor additions. Click for full image

Plan view 12
Viewpoint 12: Click image above to see full version of drawing showing where photos were taken and the direction of view. Click for full image

     

Keewaydin Expansion Update #10 - January 8, 2013

The site has been busy the last few weeks and many parts of the Keewaydin addition are underway, including the gym, the first and second floor structural steel and the auditorium.

The gym has many activities going on from roof installation to brick cladding. The gym roof was installed and completed last week, and on the lower half of the exterior gym walls architectural precast panels are being prepared to be installed. Exterior brick will soon follow above and continue on the other elevations. Near the gym, the exterior of the trash and receiving areas are being cladded with brick and will be completed this week.

Moving to the west, the structural steel is erected for most of the north portion of the building addition. Steel decking is being placed on the second floor near the lobby and mechanical areas, and will continue to be installed over the next few weeks. The steel roof joists are being installed over the classrooms and have already been installed over the auditorium.

In addition to the roof joist at the auditorium, large racker beams were installed to hold precast concrete for stadium seating. The precast concrete is now in place and links to the second floor common and mechanical areas. Over the next few weeks steel work will start to wrap up, and the building will start to be enclosed from the roof down.

Text,and photos in this update courtesy of RSP Architects, Minneapolis, MN.
Photos and plans may have been modified to fit the Web format.
(Received1/10/13)

 

 

Photo 10-1
Photo 10-1: Taken from the second floor entry into the Auditorium and looking at the stage location. Beyond the stage will be new classrooms and to the right is the double height lobby space.Click for larger image

Photo 10-2
Photo 10-2: View from the west central corridor between new offices, computer lab and classrooms. Click for full image

Plan view 10
Viewpoint 10: Click image above to see full version of drawing showing where photos were taken and the direction of view. Click for full image

     

Expansion Update #9 - December 14, 2012

The snow did not stop the progress at the Keewaydin School, the snow on the gym roof has been removed and the site has been shoveled. There are several projects underway at the site this week, including work at the gym, steel installation and exterior cladding, and will continue through winter break.

The gym has many activities in process, including placing concrete masonry units at the large pocket door enclosure and gym roof installation. These are scheduled to be completed over the next week. The gym will then be enclosed for the winter, which will allow for the start of interior elements.

Over the next few weeks the exterior brick will be placed along the gym and trash/receiving areas. This week brick was placed along the Trash/Receiving area.

Steel continues to be erected at the north portion of the building addition. The large columns at the edge of the courtyard are installed creating the double height lobby space, adjacent to the Auditorium. Formwork for the Auditorium walls are in place and concrete will be poured next week. Precast stadium seating will be installed in the next couple weeks.

Text,and photo 9-2 in this update courtesy of RSP Architects, Minneapolis, MN.
Photos and plans may have been modified to fit the Web format.

(Received12/20/12)

 

Photo 9-1
Photo 9-1: Looking NE at the southwest corner of building from 30th Ave. Steel has been erected for the first floor lobby, breakout spaces, second floor Classrooms and other adjacent spaces. Click for larger image

Photo 9-2
Photo 9-2: Looking SW from the ball fields. At the northeast corner of gym, a fluid air barrier has been sprayed on the lower half of gym walls. Installation of exterior brick will soon follow. Click for larger image

 

     

Expansion Update #8 - November 30, 2012

The last few weeks have been mostly about steel at the Keewaydin campus. The campus now has 80% of the steel on site for its new addition.

Steel started at the gym last week, with the first to be erected the gym steel joists and then the gym roof decking. The decking is currently being installed and will be finished by the end of the week.

Steel is also being erecting at the northeast portion of the new addition. There are a several columns and beams that have been installed. Steel construction will continue over the next several weeks.

Other activities on site include the pouring of the foundation for planters in courtyard and completion of the slab in the receiving area. Mechanical work and landscaping for the courtyard will continue over the coming weeks. 8-1: View from the southeast entry into the gym, the steel joists are erected, decking is staged and the decking is now being welded to the joist. 8-2: Columns and beams erected at the northeast portion of building. Columns and beams outline the east link, 2nd floor mechanical room, and corridor connecting to the gym

 

Text, plan drawing and photo in this update courtesy of RSP Architects, Minneapolis, MN.
Photos and plans may have been modified to fit the Web format by NENA Staff.

(Received12/20/12)

 

 

Photo 8-1
Photo 8-1: View from the southeast entry into the gym, the steel joists are erected, decking is staged and the decking is now being welded to the joist. Click for larger image

Photo 8-2
Photo 8-2: Columns and beams erected at the northeast portion of building. Columns and beams outline the east link, 2nd floor mechanical room, and corridor connecting to the gym Click for larger image

Viewpoint 8
Viewpoint 8: Click image above to see full version of drawing showing where photos were taken and the direction of view. Click for full image

     

Expansion Update #7 - November 13, 2012

The Keewaydin expansion is on schedule as work continues on the courtyard and on the concrete slabs in the receiving and kitchen area, while site preparation is done for the arrival of steel.

After the excavation of the courtyard last week, work has begun on prepping the courtyard for footings and retaining walls. The footings and retaining walls will be poured this week with the courtyard set to be paved next week. Trees are scheduled to be planted over the next few weeks. Last week the trash area floor slab was poured and prep for the receiving area had begun. The concrete slab will be poured in the receiving area and near the kitchen early this week, leaving space for steel construction to begin later this week.

Steel will begin to arriving on site this week for the gym area followed by the main part of the building. The steel will be erected over the next several weeks.

 

Text, plan drawing and photo in this update courtesy of RSP Architects, Minneapolis, MN.
Photos and plans may have been modified to fit the Web format by NENA Staff.

(Received12/20/12)

 

 

Photo 7-1
Photo 7-1: Next to the newly poured trash area slab is the exit stair on the south side of the gym. Bollards and concrete blocks separate the exit stair and trash area.  Click for larger image

Photo 7-2
Photo 7-2: The now-complete underground plumbing for the first floor bathrooms. The bathroom area will be backfilled followed by a concrete slab. Click for larger image

Viewpoint 7
Viewpoint 7: Click image above to see full version of drawing showing where photos were taken and the direction of view. Click for full image

     

Expansion Update #6 - November 1, 2012

Many activities are currently underway at the Keewaydin campus, including the pouring of the gym floor, paving at the south parking lot, and work beginning on the courtyard.

With the walls up and the floor poured, the gym is ready for the installation of steel. Steel for the gym will be arriving on site over the next several weeks and installation will then begin. This will include steel for the gym joists and decking.

The last of the underground plumbing is being finished up and the receiving/kitchen area will be backfilled. Once backfilling is complete in the Trash/Receiving areas, concrete blocks will be in-filled along the south wall.

The south end of the site was paved with its first coarse of asphalt, from the receiving area to south parking lot, along with curbs and gutters. The final coarse will be applied in the summer. Work on the courtyard has begun and includes site excavation of existing sidewalks and site grading. Work will continue on the courtyard over the next several weeks.

 

Text, plan drawing and photo in this update courtesy of RSP Architects, Minneapolis, MN.
Photos and plans may have been modified to fit the Web format by NENA Staff.

(Received11/05/12)

 

 

Photo 6-1
Photo 6-1: Viewing from the north entry of the gym, the gym floor is being poured and leveled. The gym floor will then be covered with plastic to allow for gradual curing. Click for larger image

Photo 6-2
Photo 6-2: Near the Trash/Receiving area, the south wall of the gym is being in-filled with concrete block. The gym walls are now 90% complete Click for larger image

Viewpoint 6
Viewpoint 6: Click image above to see full version of drawing showing where photos were taken and the direction of view. Click for full image

     

Expansion Update #5 - October 18, 2012

Over the last few weeks the gym walls have gone up, utilities and underground plumbing are underway, and site preparation for floor slabs will start.

The gym walls are 90% constructed, and the interior will be cleaned and prepped for the gym floor slab early next week

. Most of the underground utilities are in place and work will continue through next week. About 80% of the underground plumbing is complete and is being inspected. After inspection, the underground plumbing will be backfilled and part of the site will be prepared for pouring the concrete floor slab. Next week a section of the concrete floor slab will be poured and over the next few weeks the gym floor slab will be poured.

 

 

 

Text, plan drawing and photo in this update courtesy of RSP Architects, Minneapolis, MN

(Received10/22/12)

 

Photo 5-1
Photo 5-1: An overall site panorama near the west entry of the expansion. Plumbing is in place at the nurseís office and bathroom, gym walls are up and backfilling of the utilities and plumbing is underway. Click for larger image

Viewpoint 5
Viewpoint 5: Click image above to see full version of drawing showing where taken and direction of view. Click for full image

     

Expansion Update #4 - October 4, 2012

With foundations in place and the exterior and interior walls beginning to be constructed, the Keewaydin expansion is starting to take shape.

In the last few weeks most of Phase 1 activities are wrapped up with the completion of the concrete footings, foundation work, foundation waterproofing, and backfilling.

Phase 2 construction is in full swing. Exterior and interior walls are under construction including the main gym walls, and the receiving and trash area. Also the underground plumbing is being installed and the utility work in progress.

[NENA Note] As of Monday, October 8, crews are excavating for the stormwater runuff detention area in the Rec Center Parking lot. The detention area will be filled with crushed rock, acting like a dry sump, then repaved.

Click for larger drawingWant to know more about the photos? Click plan at left to see larger version of drawing showing where taken and direction of view.

 

 

 

Text, plan drawing and photos in this update courtesy of RSP Architects, Minneapolis, MN

(Received10/08/12)

 

Photo 4-1
Photo 4-1: North and East exterior gym wall and northeast exit stair from gym. Brick similar in color and shape to the existing building will be used as exterior cladding. Click for larger image

Photo 4-2
Photo 4-2: Interior corridor walls, adjacent to the gym, are under construction. The cafeteria and Auditorium walls are also under construction (not in picture).Click for larger image

     

Expansion Update #3 - September 18, 2012

As fall quickly approaches Keewaydin Campus has seen an influx of construction activity to finish the foundations and footings for the new addition. 

Waterproofing on exterior foundation walls is complete on the north, east and south walls and backfilling is taking place.  Excavation of the west wall took place last week and will be followed by footings and foundations.  The waterproofing along the southwest corner and west foundation wall will be completed soon.  Pouring of the interior footings started last week and will be complete in the next few weeks.

Once the west gym wall and the remainder of the interior footings are complete, underground plumbing will begin along with other Phase 2 activities.

Text and photos in this update courtesy of RSP Architects, Minneapolis, MN

(Received 9/24/12)

 

Photo 3-1
Photo 3-1: North common wall has been waterproofed and backfilled. Click for larger image

Photo 3-2
Photo 3-2: East gym wall, where he interior backfill is now complete.Click for larger image

     

Expansion Update #2 - September 6, 2012

Over the past few weeks the Keewaydin Campus has remained busy with construction activities, varying from the completion of the geopiers and helical piers to the start of visible footings and foundations for the expansion.

With most of the site work complete, the footings and foundation walls are progressing along the south side of the building and back fill is taking place along the North common wall and east/ west wing. The exterior and interior foundations are scheduled to be complete within the next couple of weeks, which will result in the completion of Phase 1 activities.

Phase 2 activities will start soon with underground plumbing which will be installed in the next few weeks and minor site excavation on the south side of the Keewaydin campus. North Common wall’s foundation, this wall will link the new addition with the existing Keewaydin Campus.

Text and photos in this update courtesy of RSP Architects, Minneapolis, MN

(Received 9/10/12)

 

Photo 2-1
Photo 2-1: North Common wall’s foundation, this wall will link the new addition with the existing Keewaydin Campus. Click for larger image

Photo 2-2
Photo 2-2: New East gym wallís footings and foundations; other foundations to be complete in the next few weeks. Click for larger image

     

Expansion Update #1 August 23, 2012

The new school year is right around the corner and in the last few weeks the Keewaydin Campus has already been full of construction activity.

Construction on the expansion started with site excavation and site work for the installation of soil reinforcements and piers. The process included the installation of about 500 Geopiers and about 90 Helical Piers, which will be completed by the end of the week.

The footings and foundation walls at the connection to east and west wing of the expansion are complete.

This week, the new gym footings and the north commonís foundation wall are being formed, and other ancillary work is being done to prepare the site for the return of students next week.

 

Text and photos in this update courtesy of RSP Architects, Minneapolis, MN

 

 

 

Photo 1-1
Photo 1-1: Installation of footing formwork for the new gym. Click for larger image

Photo 1-2
Photo 1-2: Installation of geopiers on east wing of expansion. With the geopiers complete, the soils are improved and ready for the installation of the concrete pad. Click for larger image

     
     
     
     
     